Family-owned & operated since 1993
Certified Great Place to Work™ 03 5442 5444
Metroid Electrical Engineering
Greenway Sewage Pump Station
Projects›Case study
Greenway Sewage Pump Station

Greenway Sewage Pump Station

Location
Greenway, ACT
Industry
Water – Municipal
Scope
Design, construction
The Project

Project overview.

This sewage pump station was built to accommodate newly released blocks in Greenway ACT. Due to the close proximity of Lake Tuggeranong, this pump station had an off line emergency storage tank. Also in a seperate pit was a magnetic flow meter to accurately record the instantaneous flow rates as well as totalised flow from the station.

Greenway Sewage Pump Station - Switchboard
FEATURES & SPECIFICATIONS

Built to spec, built to last.

Board specifications

  • 2 x 2.4kW pumps on VSDs
  • Allen Bradley Softstarters
  • Allen Bradley 12” HMI
  • Allen Bradley MicroLogix PLC

Have a project like this?

Proven ExpertiseSystemised ExecutionGenuine People
Request a quote →